How the construction of the green metro line is progressing and when specialists will begin work on the new stations “Komarovskaya” and “Persepa” were discussed at a meeting with the chairman of the Minsk City Executive Committee, Vladimir Kukharov, the agency “Minsk-News” reports.
In the capital, construction of the Zelenoluzhskaya metro line continues. Two mechanized complexes, “Alesya” and “Maria”, are simultaneously laying tunnels that will connect three new stations (“Komarovskaya”, “Persepa”, “Park Druzhby narodov”). Each can advance about 250 meters per month.
— “Alesya” is currently in the area of the “Belarus” hotel. “Maria” has already gone beyond the boundaries of “Komarovskaya”, which will be located under the intersection of M. Bogdanovich and V. Khorozyi streets, and is moving toward “Persepa,” clarified Ivan Mikulski, director of the Minsk Metro Construction Directorate. — By the way, excavation work at “Komarovskaya” and “Persepa” is continuing. The construction of the station complexes themselves is scheduled to begin in 2027.
At the same time, specialists are carrying out monolithic work at the “Park Druzhby narodov” station. They plan to finish this stage already in January. Particular attention is also being paid to the turnback sidings where trains will be turned around. The backfill of the soil is planned to be carried out at the beginning of 2027.
— The task is complicated by difficult weather conditions and waterlogged soils. To cope with this type of load, water-reduction systems operate around the clock at the construction sites, added Mikulski.
In addition, they have already begun purchasing the necessary equipment for the future stations.
They have not overlooked the fourth (ring) metro line either. The design decisions for its preparatory phase are now in the final